Annex C
Detailed Financial Breakdown
OriLife Platform: Detailed Budget Breakdown
Document: Annex C — Detailed Financial Breakdown
Version: v4.2
Updated: April 24th, 2026
Reference: GS-ORILIFE-GA-01
Proposer: Nguyen Hung Son— DDC Holdings
Status: Public — Attached to Governance Action
Total Budget: 2,400,000 ADA = $600,000 USD,
Anchor Rate: $0.25 USD/ADA
Milestones: 9 (M0–M8)
Budgeting Principles
1. Personnel is the largest expense — and rightly so
The current technical team is operating at maximum capacity. To complete 180 million fruits across 12,000 ha before the end of 2026, additional specialized engineers and field operations staff are needed. Vietnamese labor costs are more efficient than international agencies, and the team uses AI-assisted workflows, achieving 2–3× the throughput of conventional processes.
2. Mobilization Advance 15% — Hire now, deploy now
M0 disburses 360,000 ADA immediately upon GA ratification so the Alliance can recruit additional staff. This advance includes automatic 90-day Clawback if M1 is not submitted, and mandatory 30-day Spending Report. Not "free money" — this is a mobilization fund with legal constraints.
3. AI costs are fine-tuning, not training from scratch
The AI budget in M1 is for specialized fine-tuning of existing small vision models for the Dak Lak durian problem — not building new models from scratch. GPU resources for fine-tuning are sourced from the LampNet community, not from the GA budget.
4. Cost-optimized audit
Strategy: Reuse Intersect's battle-tested Escrow template → audit only customization (~$5–15K instead of $25K+) → apply for Intersect Community Audit Fund in parallel → Bug Bounty post-launch supplement.
5. Budget anchored in USD at a conservative rate
All actual costs are denominated in USD. The $0.25/ADA rate was chosen below market price to ensure sufficient budget even if ADA corrects. Symmetric commitment: Alliance self-funds if ADA drops, returns/reinvests surplus if ADA rises.
6. Every expense has documentation
GreenSun Tech commits to providing complete VAT invoices (Vietnamese vendors), invoices/receipts (international vendors), and contracts/SoWs (contractors) as requested by IOB.
7. Compensation allocation philosophy
All Alliance members participating in the project — including Duc Tiger and Nguyen Hung Son— receive reasonable compensation from the GA budget. Compensation is allocated by role, actual workload, and measurable contribution at each milestone — not as a fixed amount predetermined for the entire project.
8. Operational fees are user-borne, not GA-funded All on-chain transaction fees generated by platform activity — VeData anchors, labor contracts, commercial escrow, Hydra audit settlements — are paid by users via MAGIC credits converted from local fiat currency. These costs are entirely separate from the 2,400,000 ADA GA budget, which covers only: infrastructure development, 12,000 ha deployment, and SDK open-sourcing.
Why individual compensation is not listed as fixed amounts:
ADA price volatility: Actual USD value received depends on the exchange rate at disbursement. Compensation must be adjusted flexibly based on the actual available USD budget.
Multi-role and flexible assignments: In a startup project with 3 companies, individuals often hold multiple roles — engineer doubling as project manager, coordinator doubling as trainer. Compensation reflects total contribution, not a single fixed job title.
Unpredictable field costs: Staff traveling to 15 highland districts face significantly different travel, accommodation, and time costs. Compensation includes offsetting these.
Efficiency measured by milestone: The Alliance commits to paying by results, not by hours. If a milestone is completed early and efficiently, compensation reflects that.
9. Contingency rates reflect risk type, not milestone size
Risk type
Rate
Milestones
AI/ML iteration — cannot be pre-modeled
25%
M1
ADA price hedge — pre-positioned
~52% buffer
M2
Field logistics — highland terrain, weather
12–57%
M4, M6
Well-defined scope — known costs
5–10%
M3, M5, M7, M8
A higher rate reflects honest uncertainty in that activity type — not lower confidence in the project overall.
Total Buffer Explained
Buffer rates vary by milestone based on the dominant risk type — not as a blanket reserve.
M1 — 25% contingency: AI fine-tuning is the highest-uncertainty activity. Reaching Recall ≥95% on a 10,000-tree multi-variety benchmark may require 1 iteration or 5; field conditions introduce variables that cannot be pre-modeled.
M2 — 52% buffer: Serves as the primary ADA price hedge. M2 is the last milestone before Mainnet launch. If ADA has depreciated significantly since M0, the Alliance draws on this buffer rather than requesting additional Treasury funds. The buffer is pre-positioned, not speculative.
M4 — 57% buffer: Highland pilot deployment carries unpredictable logistics — road conditions, harvest timing, farmer availability across 1–2 districts. Buffer funds emergency team reinforcement if onboarding stalls. M4 is the milestone with the highest real-world friction; underfunding it risks cascading delays to M6 and M7.
M5 — 54% buffer: SDK open-sourcing scope depends on the state of the codebase after M3 audit. If audit surfaces architectural changes, the buffer covers re-engineering without delaying M6.
M3 and M7 carry tight buffers (5% and 15%) because their scope is well-defined: M3 is audit + Mainnet deployment with known costs; M7 is logistics and infrastructure scale with field-tested data from M4 and M6.
All buffers are locked in Intersect's Escrow. Unused portions follow Surplus policy (Annex D, Scenario 6): Alliance reimbursement first, then contingency, then ecosystem reinvestment — public report within 14 days after M8.
Transparency commitment: Total personnel costs per milestone are reported in monthly Spending Reports and milestone Completion Reports, with valid documentation (contracts, invoices). IOB has the right to request detail on any line item.
Summary by Milestone
#
Milestone
ADA
USD
%
M0
Foundation + Mobilization Advance
360,000
$90,000
15.0%
M1
Alpha — 750,000 sample fruits
260,000
$65,000
10.8%
M2
Beta App + Contract Freeze
220,000
$55,000
9.2%
M3
Audit + Mainnet Launch
180,000
$45,000
7.5%
M4
Pilot — 7.5 Million fruits / 500 ha
280,000
$70,000
11.7%
M5
SDK Open + Multi-app
200,000
$50,000
8.3%
M6
Beta Rollout — 45 Million fruits / 3,000 ha
260,000
$65,000
10.8%
M7
Mass Rollout — 180 Million fruits / 12,000 ha
280,000
$70,000
11.7%
M8
Global Integration + Sustainability
360,000
$90,000
15.0%
Total
2,400,000
$600,000
100%
Constraint checks:
✅ M0 = M8 = 15% (symmetric advance ↔ sustainability)
✅ No milestone > 20%
✅ Logarithmic scaling: 750K → 7.5M → 45M → 180M fruits
Summary by Category
Category
USD
%
Additional personnel (full project recruitment)
$220,000
36.7%
Field operations (DDC Holdings)
$105,000
17.5%
Technical infrastructure & scaling
$72,000
12.0%
Security audit + Bug Bounty
$20,000
3.3%
AI fine-tuning + Data collection & labeling
$28,000
4.7%
Legal, compliance & registration
$25,000
4.2%
SDK, integration & documentation
$22,000
3.7%
B2B integration & international partnerships
$20,000
3.3%
Impact assessment & reporting (third-party)
$15,000
2.5%
Community, AMA & communications
$12,000
2.0%
Consolidated contingency
$61,000
10.2%
TOTAL
$600,000
100%
M0 — Foundation + Mobilization Advance
360,000 ADA · $90,000 · 15.0% · May Week 1–2
Recruit additional staff, establish legal and technical infrastructure, deploy Escrow contract.
Breakdown
0.1 Personnel — Immediate Recruitment
Item
Unit
Qty
Unit Price
Total
Senior AI engineer (6-month contract)
person
2
$3,500/mo × 1 mo advance
$7,000
Backend/smart contract engineer (6-month contract)
person
2
$3,000/mo × 1 mo advance
$6,000
Mobile engineer (6-month contract)
person
1
$3,000/mo × 1 mo advance
$3,000
SDK engineer + Technical writer
person
1
$2,500/mo × 1 mo advance
$2,500
DDC field coordinator
person
2
$1,200/mo × 1 mo advance
$2,400
DDC field staff
person
6
$800/mo × 1 mo advance
$4,800
Total personnel M0
$25,700
Note: This is the first month's recruitment cost. Subsequent months are covered within M1–M7 respectively.
0.2 Legal & Setup
Item
Qty
Unit Price
Total
Notarized MOU between 3 Alliance companies
1
$2,000
$2,000
Draft new employment contracts (14 positions)
14
$200
$2,800
Additional legal registrations (permits, tax)
1
$1,500
$1,500
Cardano/crypto compliance legal counsel
1
$3,000
$3,000
Total legal M0
$9,300
0.3 Technical Infrastructure Setup
Item
Qty
Unit Price
Total
Escrow smart contract development + Preprod deploy
1
$5,000
$5,000
Dedicated Cardano Preprod node (6 months prepaid)
1
$200/mo × 6
$1,200
Schema Registry (Apicurio) setup
1
$500
$500
CI/CD pipeline + GitHub Actions
1
$800
$800
Additional development devices (test phones)
10
$150
$1,500
Total infrastructure M0
$9,000
0.4 Operations & Communications
Item
Qty
Unit Price
Total
Dak Lak office space (6 months)
1
$500/mo × 6
$3,000
Intersect Forum post + Community call
1
$500
$500
HCM ↔ Dak Lak travel for kickoff
4 trips
$300
$1,200
Total operations M0
$4,700
0.5 Contingency M0 (15%)
Item
Calculation
Total
Contingency
15% × $48,700
$7,305
M0 risks: Recruitment slower than expected, additional legal fees.
M0 Summary
Category
USD
First-month personnel
$25,700
Legal & setup
$9,300
Technical infrastructure
$9,000
Operations & communications
$4,700
Contingency (15%)
$7,305
TOTAL M0
$55,705
Budget M0
$90,000
Buffer
$34,295
Buffer M0 ($34K): For cases requiring additional hires or second-month payroll before M1 disburses. Unused portion rolls to M1.
M1 — Alpha: Identify 750,000 Sample Fruits
260,000 ADA · $65,000 · 10.8% · May–June
Breakdown
1.1 Personnel (project months 2–3)
Item
Unit
Qty
Unit Price
Total
AI engineer (continued from M0)
person × month
2 × 2
$3,500
$14,000
Pipeline operations engineer
person × month
1 × 2
$3,000
$6,000
Total personnel M1
$20,000
1.2 Field Data Collection
Item
Unit
Qty
Unit Price
Total
DDC field team (reinforced)
person × day
5 × 10
$80
$4,000
Field travel (fuel, vehicles)
trip
30
$25
$750
Additional equipment (power banks, mounts)
set
5
$50
$250
Total collection
$5,000
1.3 Data Labeling
Item
Unit
Qty
Unit Price
Total
Semi-automated labeling (CVAT)
image
50,000
$0.15
$7,500
Human quality review
hour
150
$15
$2,250
Labeling platform fees
month
2
$200
$400
Total labeling
$10,150
1.4 Independent Benchmarking
Item
Qty
Unit Price
Total
Third-party AI benchmarking
1
$5,000
$5,000
A/B testing infrastructure
1
$500
$500
Benchmark report writing
3 days
$200
$600
Total benchmarking
$6,100
1.5 Core Database Infrastructure
Item
Qty
Unit Price
Total
PostgreSQL 16 cluster (3 nodes, 2 months)
1
$600/mo × 2
$1,200
Milvus DiskANN cluster (2 months)
1
$800/mo × 2
$1,600
CDN for OTA model updates
1
$300
$300
Total infrastructure
$3,100
1.6 Contingency M1 (25%)
Item
Calculation
Total
Contingency
25% × $44,350
$11,088
High contingency (25%) because AI fine-tuning cannot precisely predict the number of iterations needed to reach Recall ≥95%.
M1 Summary
Category
USD
Personnel
$20,000
Field data collection
$5,000
Data labeling
$10,150
Independent benchmarking
$6,100
Database infrastructure
$3,100
Contingency (25%)
$11,088
TOTAL M1
$55,438
Budget M1
$65,000
Buffer
$9,562
M2 — Beta App + Contract Freeze
220,000 ADA · $55,000 · 9.2% · June–July
Breakdown
2.1 Personnel
Item
Unit
Qty
Unit Price
Total
Mobile engineer (Android production)
person × month
1 × 2
$3,000
$6,000
Aiken smart contract engineer
person × month
1 × 2
$4,000
$8,000
Backend engineer (PhoenixKey integration)
person × month
1 × 1.5
$3,000
$4,500
Total personnel M2
$18,500
2.2 Testnet Infrastructure
Item
Qty
Unit Price
Total
Dedicated Cardano Preprod node
2 months
$200
$400
Milvus test cluster
2 months
$500
$1,000
PostgreSQL test
2 months
$150
$300
API Gateway (test environment)
2 months
$100
$200
Total infrastructure
$1,900
2.3 Field Testing — 1,000 Trees
Item
Qty
Unit Price
Total
DDC team (reinforced)
5 people × 2 weeks
$200
$2,000
Travel & logistics
15 trips
$40
$600
4G SIM cards for test devices
10
$10
$100
Total testing
$2,700
2.4 Documentation & Demo
Item
Qty
Unit Price
Total
Demo video production
2 days
$200
$400
English + Vietnamese subtitles
6 hours
$50
$300
Total documentation
$700
2.5 Contingency M2 (12%)
Item
Calculation
Total
Contingency
12% × $23,800
$2,856
M2 Summary
Category
USD
Personnel
$18,500
Testnet infrastructure
$1,900
Field testing
$2,700
Documentation & demo
$700
Contingency (12%)
$2,856
TOTAL M2
$26,656
Budget M2
$55,000
Buffer
$28,344
Large buffer ($28K): Contingency for smart contract redesign before freeze, or PhoenixKey integration complexity beyond expectations.
M3 — Audit + Mainnet Launch
180,000 ADA · $45,000 · 7.5% · July
Breakdown
3.1 Security Audit
Item
Qty
Unit Price
Total
Aiken smart contract audit (independent firm)
1
$15,000
$15,000
Post-fix review (if needed)
5 hours
$300
$1,500
Bug Bounty program setup (Immunefi)
1
$2,000
$2,000
Total audit
$18,500
Note: $15K is the reference price for a medium-complexity Aiken audit. If Intersect template reuse succeeds, only customization is audited → reduced to $5–8K. If Intersect Community Audit Fund covers it → potentially free. Savings go to Bug Bounty.
3.2 Personnel
Item
Unit
Qty
Unit Price
Total
Backend engineer (Mainnet + VeData)
person × month
2 × 1
$3,000
$6,000
Midnight integration specialist
person × month
1 × 1
$4,500
$4,500
Total personnel M3
$10,500
3.3 Production Infrastructure — Mainnet
Item
Qty
Unit Price
Total
Dedicated Cardano Mainnet node (4 months)
1
$250/mo × 4
$1,000
PostgreSQL HA cluster (3 nodes, 4 months)
1
$600/mo × 4
$2,400
Milvus cluster (initial phase, 4 months)
1
$800/mo × 4
$3,200
API Gateway + CDN (4 months)
1
$300/mo × 4
$1,200
Prometheus + Grafana monitoring
4 months
$100
$400
Total infrastructure
$8,200
3.4 BCT Portal Connection (Circular 11)
Item
Qty
Unit Price
Total
API integration with BCT Portal
5 days
$250
$1,250
BCT technical consultation
2 sessions
$500
$1,000
Total BCT
$2,250
Note: Hydra Head initialization for Path B Audit Settlement (~0.58 ADA one-time) and VeData Mosaic CID Subscription API deployment are included in infrastructure setup budget. Daily operational cost of Path B: ~2.70 ADA/day — included in infrastructure line item.
3.5 Contingency M3 (8%)
Item
Calculation
Total
Contingency
8% × $39,450
$3,156
M3 Summary
Category
USD
Security audit
$18,500
Personnel
$10,500
Production infrastructure
$8,200
BCT Portal connection
$2,250
Contingency (8%)
$3,156
TOTAL M3
$42,606
Budget M3
$45,000
Buffer
$2,394
M4 — Pilot: 7.5 Million Fruits / 500 Ha
280,000 ADA · $70,000 · 11.7% · July–August
M4 is the first milestone with significant field costs — onboarding 500 farm households in 1–2 districts.
Breakdown
4.1 DDC Holdings Personnel
Item
Unit
Qty
Unit Price
Total
Field coordinator
person × month
1 × 2
$1,200
$2,400